Published on: 12 November 2019

Construction output volume increased by 17.8% in September

The volume of construction output, based on raw data was 17.8% higher in September 2019 than a year earlier. The volume of output increased in both main groups of construction: in the construction of buildings by 18.7% and in civil engineering works by 17.2%. Based on seasonally and working day adjusted indices, construction output increased by 5.2% compared to the August data. In the 3rd quarter construction producer prices increased by 9.5% compared to the same period of the previous year.

In September 2019, compared to the same month of the previous year:

The volume of output increased in both main groups of construction: in the construction of buildings by 18.7% and in civil engineering works by 17.2%. In the construction of buildings the increase was due to residential, cultural and industrial buildings, in civil engineering works road- and railway constructions generated the growth.

Out of the divisions of construction, output volume increased by 16.9% in the construction of buildings, by 21.1% in civil engineering. Output grew in specialised construction activities by 16.2%.

The volume of new contracts increased by 60.0%, within this the volume of new contracts concluded in the construction of buildings went up by 16.6%, in the construction of civil engineering works the volume grew by 98.8% year-on-year. High value contracts regarding road constructions and flood-prevention systems have been concluded in September.

The volume of the September month-end stock of contracts at construction enterprises decreased by 7.6% compared to the September 2018 data. The stock of contracts volume increased by 53.8% for the construction of buildings and decreased by 20.6% for the construction of civil engineering works.

In the first nine months of the year, compared to the same period of the previous year:

The volume of output of construction grew by 28.0%.

Construction Producer Prices:

In the 3rd quarter, within the divisions of construction, prices increased by 10.7% in the construction of buildings, by 8.8% in civil engineering works and by 9.3% in the greatest weight carrying specialized construction activities compared to the same period of the previous year.

Construction prices were 1.7% higher than in the previous quarter.

Output of construction

Period Output of construction
volume indices value at current prices, billion HUF
original seasonally and working day adjusted
corresponding period of the previous year =100.0% 2015 = 100.0% previous month = 100.0%
2015103.0100.0100.2x2 171.7
201681.281.180.5x1 812.7
2017129.7105.2103.6x2 491.5
2018121.3127.5126.0x3 321.3
2018January141.366.0123.5104.1137.9
February121.571.1112.891.3148.2
March98.386.494.984.2180.8
April113.693.3108.1113.8197.0
May113.9120.3118.2109.3256.2
June123.9144.2127.5107.9309.2
July134.2127.6128.0100.4277.1
August124.7152.1139.5109.0329.3
September124.1170.6135.897.3370.3
October119.3153.0138.3101.8338.8
November127.2164.8144.0104.1369.5
December118.8181.0141.998.6406.9
2019January123.581.5151.4106.7188.6
February146.6104.3163.1107.7240.2
March167.5144.8158.096.9334.6
April139.7130.4151.696.0303.2
May126.9152.8151.099.6358.0
June119.1171.7152.6101.1405.7
July133.3170.1168.5110.4404.7
August108.5165.1152.890.7391.2
September117.8201.0160.7105.2477.9
January–September128.0146.8156.6x3104.0